Read used case-packer ratings without mixing bottles per hour, cases per minute and machine cycles. Use an explicit pack count and a common production window.

Case-packing offers can quote containers per hour, cases per minute or cycles per minute. These values can only be compared after the pack pattern and loading arrangement are known. Keep the seller's original wording visible and ask for clarification wherever the unit is ambiguous.

01

Identify what the number counts

Ask whether the figure counts individual bottles, completed cases, loading cycles or another item. Confirm the number of cases loaded in each cycle. Do not interpret CPM from the letters alone; the supplier should write out the unit and identify the configuration to which it applies.

02

Use one explicit conversion example

Hypothetical example: 12 bottles per case at 20 completed cases per minute equals 240 bottles per minute, or 14,400 bottles per hour while that rate is maintained. This is a mathematical equivalence, not a rating for a listed machine or evidence of shift output.

Hypothetical inputCalculation
12 bottles in each casePack count is fixed for this example
20 completed cases per minute12 × 20 = 240 bottles per minute
240 bottles per minute240 × 60 = 14,400 bottles per hour
03

Treat cycles as a separate measurement

A loading cycle may handle more than one case, depending on the machine. Sidel describes multi-case loading configurations in its top-loading range. For a used packer, request the actual head arrangement, pack pattern and supplied tooling before converting cycles into completed-case output.

04

Measure acceptable packs over the same window

Ask for run duration, case count, stops and rejected packs together. Record whether upstream product supply and downstream case handling were included in the trial. A loading mechanism running freely can demonstrate motion without proving the output of the connected packing process.

05

Compare formats separately

Keep separate rows for each bottle and case pattern in your production plan. Include changeover work and any missing tooling as distinct issues. An offer should identify which results are stated, which were observed and which still require a trial with your samples.

Buying checklist

  • Unit written out by the seller
  • Bottles per case and cases per loading cycle
  • Configuration linked to the speed figure
  • Common window for good cases, stops and rejects
  • Upstream and downstream scope of the run
  • Separate evidence for each proposed format